Tyra Southeast is moving full steam ahead

23/09/2013

As announced in April 2013, Maersk Oil awarded Bladt Industries the contract of supplying the engineering, procurement and construction (EPC) of a topside with a four-legged jacket structure as well as a bridge linking the new topside with the existing Tyra central processing platform.
The project is starting to take shape, as the Bladt team is presently working on assembling the pile clusters for the jacket structure. Furthermore, the topside is being assembled as we have received the first components from our subcontractors.
Operating with a fairly short time-frame on a complex project, the workers at Bladt Industries are working efficiently to make sure that quality and precision are at the highest standard at all times. The topside, jacket and connecting bridge, which Bladt Industries are fabricating for Maersk Oil, are scheduled to leave Bladt Industries’ facilities in Aalborg in May 2014.