Arcadis Ost
Germany (247 MW)
Parkwind and Bladt Industries have signed an agreement for the design, fabrication, and installation of the Arcadis Ost 1 substation in the German Baltic Sea. The platform is jointly developed and will be jointly operated with 50Hertz, the responsible Transmission System Operator (TSO) for connecting the offshore wind farms in the German Baltic Sea.
The offshore wind farm, 19 km off the island of Rugen is expected to start installation activities in 2022.
Bladt Industries is to deliver the complete substation for Parkwind, with Semco Maritime and ISC as key partners. Semco Maritime will be responsible for the design and implementation of the entire electrical systems while the structural design will be delivered by ISC Engineering.
FACTS
Client:
Scope:
Year:
Weight:
Type of contract :