Hornsea One

Great Britain (752 MW)

Reference

In May 2016, Bladt Industries and Semco Maritime won an order for the supply of three substations for the
Hornsea Project One Offshore Wind Farm – a DONG Energy project.

The construction contract is unique and historical, as it is the first time in Bladt Industries’ and their long-term partner Semco Maritime’s history that a contract has been signed for three substation topsides at the same time.

The first substation will be ready for delivery early 2018. Upon installation and take over, Hornsea Project One Offshore Wind Farm will be located in the North Sea approximately 120 kilometres off the coast of Yorkshire in Great Britain.

Bladt Industries is responsible for the construction of steel structures for all substations, while Semco Maritime will facilitate the production of LV electrical works, including E&I, design, onshore construction and offshore commissioning

FACTS

Client:

Ørsted

Year:

2018

Location:

Great Britain

Scope:

Fabrication of three offshore substations

Output:

752 MW

Weight:

2,800 t / Each

Type of Contract:

PC
For more information, please contact
GQ0A1243 Ny

Troels Jensen

Senior Vice President, Substations

Tel.: +45 2171 4323

Email: